Complete thermal, structural and general renovation of a listed building comprising a 2-storey base, topped by 2 8-storey towers, built on
levels, built on 5 basement levels. Change of use of the office towers into 75 residential units. Development of 3 shops on the ground floor and 2 offices on the mezzanine floor.

Information

Developer

AXA Anlagestiftung Kommerziell, représentée par

AXA Investment Managers Schweiz AG, Zurich

Services rendered by HRS

Development and total undertaking with guaranteed costs, deadlines and quality

Architect

Burckhardt+Partner SA, Geneva

Size

Building volume 49’143 m³

Floor area 15’587 m²

Total cost

CHF ~ 34,5 Mio.

Construction period

February 2021 – June 2024