05.06.2025 | Rochemont
We have just installed the steel framework for the footbridge that will link the new Pictet building to the existing one.
One of the highlights of the project was the installation of the 20-metre-long, 3-metre-high main beam, weighing more than 15 tonnes - a large-scale operation that was successfully completed thanks to exemplary coordination.
A big well done to the teams involved, and in particular to our partners:
1. HOTIMETAL, for the manufacture and installation of the framework
2. MATTHEY PETIT, for the meticulous lifting operations.
This footbridge symbolises the junction between the existing and the future of the site, and marks a major step forward in this ambitious project.