Estavayer-le-Lac (VD)

MEP Gare-Casino

Construction of a building comprising a large reinforced concrete reinforced concrete base housing a level of commercial and administrative areas. On this base are 3 volumes of 40 flats in timber frame construction. An underground car park with 105 underground car park.

Information

Developer

Transports publics fribourgeois Immobilier (TPF Immo)

SA, Givisiez

Services rendered by HRS

Development and total undertaking with guaranteed costs, deadlines and quality

Architect

Nicolas de Courten Architectes Sàrl, Lausanne

Size

Building volume 48’159 m³

Floor area 12’069 m²

Total cost

CHF ~ 38.0 Mio

Construction period

September 2023 - May 2026